Trumbull BOE: 'Disappointed' at Progress in THS Renovations

The Board of Education expressed its dissatisfaction to the Building Committee in October, before Hurricane Sandy hit. A new hopeful end date is June 2013.

The school district is focusing on technology as Trumbull High School renovations are projected to wrap up as late as June 2013, with the conclusion of punch list items.

School officials made the criticism before Hurricane Sandy hit, which closed school for a week.

"Technology will definitely be a focal point," said Schools Supt. Ralph Iassogna. The district is working to obtain refurbished computers from IBM, the former employer of a current school district worker.

But some THS work, especially technology setup, is being done by staff rather than contractors.

"They are doing the work of contractors and that should not occur," said School Board Vice Chairwoman Deborah Herbst.

Recent flooding has also knocked out Internet to some of the school's labs. Repairs have been made but service is sporadic at times.

"We have reached a point where we've got to move forward in an organizaed fashion," Iassogna said.

School officials said previous work has been focused in different areas, such as the senior lounge and the auditorium. Now the entire school needs to be completed.

"They've got to tie it together. The magnitude of the renovation is the whole building," Iassogna said.

In the end, the school board voted to tell the building committee:

"The BOE is disappointed with the lack of progress in completing essential construction activities at THS, the lack of organization and diligence by the design team and construction manager and the failure of the architect and construction manager to adequately mitigate the disruption of school operations."

At the Building Committee's recent meeting, District Technology Director Jeff Hackett told the committee:

  • There is no WiFi in the building
  • Video on Demand is not purchased yet
  • Laptops have not been purchased
  • Channel 17 is not on the air yet.

Hackett said Charter is scheduling the connection to a single cable and hasn't proceed for reasons he does not know. But, he added, AT&T Uverse wiring is set up.

Hackett also noted that 90 percent of the infrastructure and all staff computers are installed, as are 85 of 97 Smartboards. The district has the remaining 12.

JR November 13, 2012 at 12:14 PM
The "recent meeting" of the building committee was October 17. Do you think any of this has changed since then? Could someone from Patch please attend the Nov 14 THSBC meeting to get an update?
Aaron Leo November 13, 2012 at 12:58 PM
Before running the story, J.R., I checked with the school's technology director and a member of the Building Committee. I assure you it's up-to-date. I will check in on the committee meeting though. Thanks.
Joe Smith November 14, 2012 at 12:05 AM
When you called O&G for a comment about the inability to meet deadlines, what did they say? What about the inability of AFB to satisfactorily manage the project, what was their comment when you called them?
Aaron Leo November 14, 2012 at 03:03 AM
AFB continues to maintain it is trying to wrap up loose ends. There are lots of construction problems from HVAC to weather damage that are being dealt with. I can't make the Committee meeting (Planning and Zoning). I will have to follow up with Al or John Barbarotta.
Joe Smith January 11, 2013 at 11:49 AM
So, how did your meeting with AFB go? I must have missed the follow up article. Maybe there was something at Monday's Town Council meeting?

Boards

More »
Got a question? Something on your mind? Talk to your community, directly.
Note Article
Just a short thought to get the word out quickly about anything in your neighborhood.
Share something with your neighbors.What's on your mind?What's on your mind?Make an announcement, speak your mind, or sell somethingPost something
See more »