patching...
Breaking: Middlebury Burglaries Prompt Police to Issue Warning »
Welcome back, Patch Blogger!

CL&P: 'We’re Still Shooting to Have 99 Percent of Our Customers Restored Sometime Sunday'

The utility said it planned to ramp up its restoration work in the coming days to meet its goal of almost total power restoration by Sunday.

 

In a tense, at times combative press conference the evening of Tuesday, Nov. 1, CL&P President Jeff Butler said that the company was sticking by its estimate that it would be able to restore power to 99 percent of its customers throughout the state by Sunday.

Butler, who joined United Illuminating Spokesman Bill Reis  and Gov. Dannel P. Malloy at a press conference at the State Armory in Hartford Tuesday evening, said that CL&P’s primary focus since Saturday’s freak October snowstorm was on "public health and safety issues," such as clearing live or downed wires from roadways, but that the utility had made "substantial progress in those areas" and that it was adding more contracted work crews daily and now planned to focus the majority of its efforts on restoration work.

"With the additional crews that we’re adding and have arrived today, with more arriving tomorrow, we’re shifting our area of focus on restoration," Butler said. "…We expect to see a significant increase in restoration rates as we shift."

Butler said that CL&P had restored more than 275,000 customers as of Tuesday, Nov. 1. He said that CL&P currently had 493 line crews – 172 from CL&P, the additional 321 outside contractors – and 393 tree crews working throughout the state, and would ramp up to 627 line crews by Wednesday, 777 by Thursday, and 837 by Friday, with an outstanding request for 300-plus additional crews from wherever the utility could find them.

Butler stood by the company’s assertion that it will have 99 percent of powerless customers restored by Sunday.

"We’re still shooting to have 99 percent of our customers restored sometime Sunday," Butler said. "…That’s what we’re pushing for, and I’ll bring whatever crews necessary as they are available to meet that target."

Reis, an United Illuminating executive, said his company had restored approximately 50,000 customers as of Tuesday and that it planned to restore the utility’s remaining 1,800 customers still without power by midnight Tuesday.

"We will work throughout the night to restore all known customer outages," Reis said.

If customers still were out of power as of 9 p.m. Tuesday, Nov. 1, he encouraged them to call UI at 800-722-5584.”

Reis said UI would then turn over its available crews to CL&P to aid in the restoration efforts.

Malloy conceded that he was frustrated by the utilities restoration efforts and that they were "not nearly fast enough," but said that the primary emphasis currently was on restoring power, and that after all Connecticut residents had their power restored would be the time for his administration and lawmakers to "analyze" the utilities performance.

"Anybody who is without power, you can’t get power back soon enough," Malloy said. "And since I’m the governor, I can’t get the utilities to get their power on soon enough. It is a frustrating experience, particularly when you understand that people are dealing with cold situations."

The current state of emergency and widespread power outages come just two months after more than 800,000 state residents lost power during Tropical Storm Irene. It took more than a week for power to be restored to the entire state after that storm, and the legislature then held a series of hearings into the utilities response.

Butler began his remarks Tuesday by addressing a report that neighboring Massachusetts had more crews working on restoration efforts than Connecticut.

He said that it was unfair to compare the two states because Massachusetts was nearly twice the size of Connecticut, and noted the number of contractor crews the utility had imported to deal with the outages, which he said would probably add up to more than 1,000 once all restoration work was completed.

Butler also addressed a report that CL&P was having trouble commissioning crews because it still had not paid outside work crews from Irene. He confirmed that there were still three invoices outstanding from that storm, but that when he heard that “rumor” yesterday he contacted the companies and that two of those invoices were paid Monday, and he believed the final invoice would be paid Wednesday.

He said he did not know the extent of the amount owed but that he was "not aware that it has been an issue" with securing contractor crews for the current storm.

Regarding whether CL&P’s current contingent of 172 line restoration crews was sufficient to cover the CL&P’s more than 1.23 million electrical customers, Butler noted that Connecticut has one of the highest electrical rates in the nation and that the utility "continually looks at its staffing."

Related Topics: CL&P, Dannel Malloy, Power Outages in Middlebury and Woodbury, and Power Restoration Estimates

Georgann

8:35 am on Wednesday, November 2, 2011

If we do not pay our payments, CL&P will shut off our power. They are a multi-million dollar monopoly company. Did the CO get paid? They should be ashamed.

Reply

Bonny

9:05 am on Wednesday, November 2, 2011

It's amazing how slow CL&P has responded to this situation. What's even more amazing is their response to getting restoration to businesses. CT has had its share of freak weather. One would think they've had plenty of experience, yet this is the outcome? Come on, haven't you learned how to handle this is a speedier fashion by now? Ashamed is correct.

Reply

Joel sobelson

9:47 am on Wednesday, November 2, 2011

What did cpl learn from Irene? How truly incompetent and poorly managed they are...except when it comes to billing !

Reply

Judie

10:05 am on Wednesday, November 2, 2011

The most frustrating part is that I have not even seen a CL&P truck come into our neighborhood or surrounding areas!! Everything is as it was after the storm was over Sunday morning!! At least their presence might give a little comfort for those of us sleeping in cold, dark houses!

Reply

ken bauco

10:30 am on Wednesday, November 2, 2011

This whole situation is completely unacceptable. Cannot believe the CEO says they're addressing the problem by bringing in crews from out of state. It is Wed., we knew the storm was coming early/middle of last week. Prepare for the worst, don't address the problem after it happens. You are a power company, providing services to millions of people. Its called disaster planning. CL&P is a terrible company.

Reply

lis

10:47 am on Wednesday, November 2, 2011

Unacceptable pace pick it up

Reply

b

10:49 am on Wednesday, November 2, 2011

When I woke up on Sunday morning and did not see one Service crew on the road I knew that we were in trouble. CL&P is irresponsible in their planning and executing and the executive team at this corporation should be held responsible for their actions,. While I can certainly sustain myself through tough times, irresponsibility is unforgivable and people in powerful positions must be held accountable for their actions as well as their in-action. BDP in Granby

Reply

liberty

11:14 am on Wednesday, November 2, 2011

Ken, that's what I've been saying if the country was to be under attack the goverment would have there fighters on standby ready and waiting for the ok..that's how it should be with storm in the northeast...we pay to much to put up with this bad management, with a million people without power where was the national guard? Why where they not distributing water, hot foods or opening more places for people to shower and have shelter. Help with gas station lines...it doesn't take a havard degree to figure this out..people really look at who you vote to put into office, that's why where going through this mess, beside How God is not happy with how we handled our resources he has provided to us..still No Power in East Hartford but power in Manchester ......

Reply

Susanne Krivit

11:22 am on Wednesday, November 2, 2011

Just for the record, it took me 9 days to get my power back after Irene. Given I was one of the last to get power back. I hope this time CL&P arrives faster.

Reply

lis

12:41 pm on Wednesday, November 2, 2011

I have not seen 1 cl&p in windsor locks get there

Reply
Patch_comments_icon

Jaimie Cura

2:23 pm on Wednesday, November 2, 2011

Taking this moment to remind Patch readers of the terms of use: http://woodbury-middlebury.patch.com/terms

Reply

Sandra

9:09 am on Thursday, November 3, 2011

I got power back last night, I'm overjoyed to say. But it galls me to see that CL&P post restoration times that are the same for everyone. They put a date that's way out there so that the expectation is that you won't have power for the weekend and then they beat their estimated time so that everyone can pat them on the back for getting the power back early. Do they think people are stupid? We can supply foreign aid to another country faster than we can restore power in our own backyard. It's disgraceful....

Reply

JM

10:20 am on Thursday, November 3, 2011

If you don't want to lose power, then cut down the trees near powerlines...it's the only way...it's obvious that the pruning that CL&P has done over the years does not work when we get big storms...enough with the name calling and complaining...do something, namely, cut down trees.

Reply

Leave a comment